Everything was green. That's what the report said.
Sometimes that means the project is healthy. Sometimes it means nobody has reported the problem yet.
I worked a mega-project where Construction declared a system 100% installed. Completion certificates were signed. On paper, it was done.
Then Commissioning started verifying it before taking ownership — and it wasn't fine. A defect that should have stopped the handover cold, but didn't.
By then, first gas was scheduled. An official visit was booked. Nobody wanted to be the one to raise the flag that cancelled a ceremony already on the calendar.
So the field found a way to get one train ready in time to hold the schedule. The board didn't know until months later. The ceremony had already happened. The vessel had already sailed.
Nobody lied on that report. The certificate was signed in good faith.
The problem wasn't dishonesty. The problem was that "Installed" and "Verified" were treated as if they meant the same thing.
They don't. One confirms the work was completed. The other confirms the system is actually ready to hand over.
Between those two words is where some of the biggest execution failures begin.